The Roosevelt Island Tidal Energy (RITE) Project

First US Grid-Connected Tidal Installation

The RITE Project

The RITE Project operated under a 10-year Hydrokinetic Pilot Project License from the Federal Energy Regulatory Commission (Project No. P-12611) and a 401 Water Quality Certification from the New York State Department of Environmental Conservation. It was the first commercially-licensed tidal power project in the United States. The project was successfully decommissioned in 2021 having achieved Technology Readiness Level 9. 

The Verdant Power 5-meter class tidal turbine system used in RITE achieved the highest standards:

Received the first third-party verification in the world of tidal turbine performance to international standards under the IECRE System.

Awarded National Hydropower Association’s 2021 Outstanding Stewards of America’s Waters (OSAW) Award for operation. 

Energy Generation at RITE

The East River is a tidal strait with strong water currents that change direction between flood and ebb tides approximately four times each day (with periods of little or no flow between tides, called “slack tide”). 

-As shown in the figure below, when the water velocity exceeds approximately 1.0 m/s (3.3 ft/s or 2 knots), the turbine blades begin to rotate and the units generate electricity for approximately 4.5 hours (red areas in figure). 

-As the tide shifts direction, the turbines yaw (turn approximately 170 degrees) to generate power from the current flowing in the opposite direction. This cycle repeats in a very predictable manner approximately every 6 hours. 

-The regular nature of tidal currents provides a significant advantage for tidal power as compared to other, less predictable resources like wind and solar power.

Proven Technology

For several years prior to the 2020 RITE project installation, Verdant Power conducted in-water testing of its turbine system, successfully demonstrating the technology as an efficient source of clean energy with the following outcomes:

  • Grid-connected power with no power quality problems
  • Fully bi-directional operation with high efficiency on both ebb and flood tides
  • Automatic control and continuous, unattended operation
  • No fouling or damage from debris

Operational and environmental monitoring data gathered through this demonstration formed the basis for Verdant Power’s application to FERC for its pilot license application.

2006-2010
2006-2010

PROOF OF CONCEPT

RITE “six-pack”- the first multiturbine grid-connected marine energy array

January, 2012
January, 2012

FERC ISSUES FIRST PILOT PROJECT LICENSE

Verdant Power’s Roosevelt Island Tidal Energy Project, was approved by the Federal Energy Regulatory Commission (FERC) for a 10-year, grid-connected operating license in New York City’s East River, following extensive consultation and commitment  to execute further environmental studies.

August, 2012
August, 2012

In-water testing with National Renewable Energy Lab

Verdant Power partnered with NREL to advance the technology readiness of the turbine with an in-water test at RITE

2010-2020
2010-2020

Enviromental Compatibility Studies

Verdant worked with federal, state and local agencies, NGOS and the Oak Ridge National Laboratory fisheries experts to develop the science related to environmental compatibility of the new technology within the US regulatory system; with nearly $4M investment in  studies and research. Throughout the adaptive management operation no  impacts have been observed

2013-2016
2013-2016

Gen5 Technology Advancement

Verdant completed technology readiness with assistance from the NY State Energy Research and Development Authority Development Authority and in May 2016, Verdant Power was awarded a US Department of Energy (DOE) cooperative agreement for a project entitled the “Integrated Development and Comprehensive IO&M Testing at RITE of a KHPS TriFrame Mount"

2018-2020
2018-2020

TRIFRAME MOUNT INSTALLATION

Verdant Power completed manufacture of three tidal power turbines as mounted on the TriFrame mount and installed and commissioned the turbines in October 2020 at its Roosevelt Island Tidal Energy site in New York's East River.

January 2021
January 2021

PERFORMANCE TO INTERNATIONAL STANDARDS

Verdant worked with the European Marine Energy Centre to conduct an off-site power performance assessment using international technical specifications. This was the first time the European Marine Energy Centre has carried out an off-site performance assessment, and the first report issued through the IEC System for Certification to standards relating to equipment for use in marine renewable energy applications

May 2021
May 2021

RETRIEVE AND REPLACE

 Verdant Power performed a retrieve and replace (R&R) operation during which one of the turbines was replaced with a rotor housing three thermoplastic blades manufactured by DOE's National Renewable Energy Laboratory (NREL) as a material component advancement; with excellent results.

December 2021
December 2021

RESULTS

Having successfully completed all technology goals, Verdant Power’s RITE project delivered over 312 MWh   of tidal power to the United States electricity grid. In accordance with the expiration of the license, the Project was decommissioned; with all infrastructure removed in compliance and to the satisfaction of regulators.